QUESTION 46
A Planning Unit has a status of First Pass; what two user types can input data?

A.    Anyone with write access to the planning unit
B.    Anyone with write access to the planning application
C.    Anyone with read or write access to the planning unit
D.    The owner of the planning unit
E.    The administrator

Answer: AE

QUESTION 47
Identify the two statements about the Planning Import security utility.

A.    Imports Planning application access for users and groups.
B.    Imports users and groups into Planning.
C.    Requires the source text file to be named PLANSECFILE.txt.
D.    Can be scheduled to run nightly using an encrypted password.
E.    Clears existing security definitions by default before the import takes place.

Answer: AC

QUESTION 48
Identify the two true statements about a sparse Entity dimension In Hyperion Planning.

A.    You cannot build alternate rollups or assign custom attributes.
B.    Base currencies are assigned to entity members.
C.    Exchange rates are assigned to entity members.
D.    Entity along with Scenario and Period make up a planning unit.
E.    Entity along with Scenario and Version make up a planning unit.

Answer: BE

QUESTION 49
In a non-multicurrency Planning application, what three things happen if all options are checked for Refresh Database?

A.    Dimension and member changes are pushed to Essbase.
B.    Cell text and supporting detail changes are pushed to Essbase.
C.    Security filters for dimensions and members are pushed to Essbase.
D.    Security filters for shared members are pushed to Essbase.
E.    Data changes are pushed to Essbase.

Answer: ACD

QUESTION 50
You are designing a monthly projection Planning application. A starting point projection file is received with the current month data. Data forms, Business Rules, and Essbase data load rules, and reports should always focus on the current projection month. What is most efficient way to design the components to reduce maintenance each month?

A.    Manually update the forms each month and use a “CurMth” substitution variable for Business Rules, Essbase data load rules, and reports.
B.    Manually update the forms each month. Use “CurMo” Global variable for Business Rules and use a “CurMth” substitution variable for Essbase data load rules, and reports.
C.    Use the Planning data form utility to update data forms and use a “CurMth” substitution variable for Business Rules, Essbase data load rules, and reports.
D.    Use a “CurMth” substitution variable for data forms, Business Rules, Essbase data load rules, and reports.
E.    Use the Planning data form utility to update data forms. Use “CurMo” Global variable for Business Rules and use a “CurMth” substitution variable for Essbase data load rules, and reports.

Answer: E